File #: 15-2051    Version: 1 Name:
Type: Report Action Item Status: Reported from Committee
File created: 12/3/2015 In control: Municipal Services Committee
On agenda: 3/8/2016 Final action: 3/16/2016
Title: Recommend to Outagamie County Highway Department to reconstruct CTH JJ from Ballard Road to Lightning Drive as follows: Reconstruct the existing roadway with concrete pavement having the following design components as shown on attached sketch and described below: o Construct a raised concrete median with two left-turn access points to the north. o Provide an enhanced pedestrian crosswalk of Edgewood Drive at the west side of the Appleton North High School (ANHS) entrance. o Construct a single-lane roundabout with east, west, north, and south approaches at the Lightning Drive intersection, with right-of-way sufficient for future roundabout expansion to two lanes, if needed. o Construct one 12-foot eastbound and one 12-foot westbound through lane (plus 2.5-foot curb and gutter) o Construct one 4-foot eastbound and one 4-foot westbound bike lane (plus 2.5-foot curb and gutter) o Construct one 5-foot concrete sidewalk along north right-of-way line and one 10-foot asphalt mult...
Attachments: 1. CTH JJ Project Goals.pdf, 2. Design map CTH JJ.pdf, 3. CTH JJ Design Concept-Todd Van Zeeland.pdf

Title

Recommend to Outagamie County Highway Department to reconstruct CTH JJ from Ballard Road to Lightning Drive as follows:

 

Reconstruct the existing roadway with concrete pavement having the following design components as shown on attached sketch and described below:

 

o   Construct a raised concrete median with two left-turn access points to the north.

o   Provide an enhanced pedestrian crosswalk of Edgewood Drive at the west side of the Appleton North High School (ANHS) entrance.

o   Construct a single-lane roundabout with east, west, north, and south approaches at the Lightning Drive intersection, with right-of-way sufficient for future roundabout expansion to two lanes, if needed.

o   Construct one 12-foot eastbound and one 12-foot westbound through lane (plus 2.5-foot curb and gutter)

o   Construct one 4-foot eastbound and one 4-foot westbound bike lane (plus 2.5-foot curb and gutter)

o   Construct one 5-foot concrete sidewalk along north right-of-way line and one 10-foot asphalt multi-use trail along south right-of-way line.

o   Construct a dedicated eastbound right-turn lane at the ANHS entrance.

o   Construct a dedicated westbound left-turn lane at Ballard Road.

o   Construct a second through lane for westbound traffic at the approach to Ballard Road.

o   Construct a second through lane for eastbound traffic from Ballard Road to the ANHS right turn lane.

o   Construct approximately 600’ of Lightning Drive north of Edgewood Drive with one northbound through lane, one southbound through lane, and a two-way-left-turn lane.

o   Construct a stormwater pond meeting state and local stormwater management requirements northeast of the Edgewood/Lightning intersection.