Title: Request to award the 2021 AWWTP Electrical Distribution Upgrades Phase 4 Project - Substation Installation contract to Van Ert Electric, Inc in the amount of $2,130,000 with a contingency of 10% for a project total not to exceed $2,343,000
Attachments: 1. 2021 AWWTP Electrical Distribution Upgrades Phase 4 - Substation Installation.pdf

Title

Request to award the 2021 AWWTP Electrical Distribution Upgrades Phase 4 Project - Substation Installation contract to Van Ert Electric, Inc in the amount of $2,130,000 with a contingency of 10% for a project total not to exceed $2,343,000