Title: Request to award Appleton Wastewater Treatment Plant M-K Tunnel Bridge Improvements Project contract to Staab Construction Corporation in the amount of $119,000 with a contingency of 10 percent for a total project cost not to exceed $130,900.
Attachments: 1. Appleton Award Letter.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Request to award Appleton Wastewater Treatment Plant M-K Tunnel Bridge Improvements Project contract to Staab Construction Corporation in the amount of $119,000 with a contingency of 10 percent for a total project cost not to exceed $130,900.