Contract 56-26 was awarded to ASTI Sawing, Inc. for the C-26 Miscellaneous
Concrete Sidewalk Sawcutting Project, in the amount of $30,000. There were
no change orders. Payments issued to date total $0. Request final payment of
$30,000.
This item was presented.
Contract 161-25 was awarded to Advanced Construction, LLC for the G-26
Pond Dredging Project in the amount of $131,766.34. There were no change
orders. Payments issued to date total $125,178.02. Request final payment of
$6,588.32.
This item was presented.
Contract 61-25 was awarded to Restoration Systems, Inc. for $1,348,594.50
with a contingency of $40,000 for S-25 Parking Ramp Repairs and
Maintenance. Change orders were approved totaling $40,000. Final contract
amount is $1,388,594.50 with a contingency of $40,000. Payments issued to
date total $1,318,115.02. Request final payment of $70,479.48.
This item was presented.
2027 Executive Budget and Service Plan Update
This item was presented.
2027 Finance Department Operating & Capital Budgets.
This item was presented.
Adjournment
8.
Van Zeeland moved, seconded by Croatt, that the meeting be adjourned at
6:26 p.m. Roll Call. Motion carried by the following vote:
5 - Firkus, Hartzheim, Van Zeeland, Fenton and Croatt
Aye: