Fenton moved, seconded by Van Zeeland, that the Report Action Item be
recommended for approval. Roll Call. Motion carried by the following vote:
5 - Firkus, Hartzheim, Van Zeeland, Fenton and Croatt
Aye:
Information Items
7.
Contract 130-25 was awarded to Northeast Asphalt Inc. for $139,094.60 for
Parks Paving Projects. Payments issued to date total $0.00. Request final
payment of $139,094.60.
This item was presented.
Contract 55-25 was awarded to Scott Lamers Construction LLC for
$486,212.08 for Y-25 Lead/Galvanized Water Service Replacement.
Payments issued to date total $236,170.61. Request final payment of
$179,296.68.
This item was presented.
Contract 159-24 was awarded to Vinton Construction for $496,345.35 for Lutz
Park Trail. Change orders were approved totaling $64,873.77. Final contract
amount is $561,219.12. Payments issued to date total $533,854.95. Request
final payment of $27,364.17.
This item was presented.
Contract 63-25 was awarded to M & E Construction, LLC for the J-25 Mini
Storm Sewer Construction Project in the amount of $250,000.00. Payments
issued to date total $0.00. Request final payment of $214,880.00.
This item was presented.
Contract Amendment #1 to McMahon for Water Treatment Facility Bulk
Hypochlorite Tank Replacement Project for additional design and construction
management services in the amount of $5,000 increasing the contract
amount from $24,000 to $29,000.
This item was presented.
Change Order #1 and #2 to Staab Construction contract as part of the
AWWTP Removable Retaining Wall / Column Storage Improvements Project
totaling $18,677 applied to remaining contract allowance resulting in
a contract deduct of -$9,054 (credit).
This item was presented.
Change Orders #4 to Sabel Mechanical as part of the AWWTP Mix Liquor
Channel Blower Replacement Project totaling $22,053.52 resulting in a
decrease in contingency from $25,275.20 to $3,221.68.
This item was presented.
Change Orders #1 through #4 to August Winter & Sons, Inc. contract as part
of the Appleton Wastewater Treatment Plant 2025 L-Building HVAC and
Receiving Station Upgrades Project totaling $90,253 resulting in a decrease in