Request to approve change orders #7, #8, and #9 to Rohde Brothers, Inc.
contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger
Replacement Project totaling -$8,001 resulting in an increase in contingency
from $23,110 to $31,111.
Request to approve change orders #5 through #8 to August Winter & Sons, Inc.
contract as part of the Appleton Wastewater Treatment Plant 2025 LBuilding
HVAC and Receiving Station Upgrades Project totaling $116,526 resulting in a
decrease in contingency from $386,084 to $269,558.
Request to approve change order #13 to Staab Construction contract as part of
the AWWTP Phase 2 Belt Filter Press Equipment Upgrades Project totaling
$31,042 resulting in a decrease in contingency from $383,130 to $352,088.
Request to approve change order #1 to Kruczek Construction contract 3-26
Unit U-26 Sewer and Water Construction with an increase of $13,510.50 for a
new contract total of $370,510.50 resulting in a decrease in contingency from
$35,000 to $21,489.50.
Request to approve change order #1 to Western Specialty Contractors contract
17-26 Unit S-26 Parking Ramp Repairs and Maintenance with an increase of
$181,000 for a new contract total of $1,387,718.50 resulting in a decrease in
contingency from $181,000 to $0.
Request to approve new Fox Cities Exhibition Center (FCEC)
Management Agreement, between the City of Appleton and Appleton Hotel
Holdings, LLC.
Request to award Sole Source Contract to Full Service Organics Management
LLC, as part of the AWWTP Anaerobic Digester Inspection, Maintenance, and
Improvements Project in the amount of $157,360 plus a 20% contingency of
$31,472 for a total cost of $188,832.
Attachments:
Request to award Sole Source purchase of a Vulcan EWP 400/600 Wash
Press to Vulcan Industries in the amount of $68,518.
Attachments:
Request to award Sole Source Contract to Dixon as part of the Matthias Tower
Coating Project in the amount of $93,962.50 plus a 5.0% contingency of $4,700
for a total cost of $98,662.50.
Attachments: