Request to award sole source contract for Parks and Recreation Building  
Furniture Upgrades to Nordon Business Environments in the amount of  
$91,681.14, with a 5% contingency of $4,584.06 for a total project not to exceed  
$96,265.20.  
Request to award the design engineering contract for the 2026 Jaycee Park  
Court Design Project to McMahon in the amount of $35,120 with a 5%  
contingency of $1,756 for a total project not to exceed $36,876.  
Attachments:  
Request to award Unit W-26 Sewer and Water Construction to Kruczek  
Construction in the amount of $2,585,585 with a 23% contingency of $60,000  
for a project total not to exceed $2,645,585.  
Attachments:  
Request to award Unit H-26 Northeast Sanitary Interceptor Sewer to PTS  
Contractors in the amount of $1,018,600 with a 20% contingency of $20,000 for  
a project total not to exceed $1,038,600.  
Attachments:  
Request to award Unit DE-26 Miscellaneous Sidewalk and Concrete Street  
Repairs to Al Dix Concrete Inc. in the amount not to exceed $1,008,850.  
Request to award Unit A-26 Concrete Paving to Vinton Construction Company  
in the amount of $3,755,429.12 with a 15% contingency of $55,000 for a project  
total not to exceed $3,810,429.12.  
Request to approve Finance Committee Report for Preliminary Resolution  
1-P-26 for Sanitary Laterals, Storm Laterals and Storm Main Construction.  
Request to approve Finance Committee Report for Preliminary Resolution  
2-P-26 for Concrete Pavement, Driveway Aprons and Sidewalk Construction.  
Request to approve Development Agreement for Comet Ridge Development  
(North Appleton Properties, LLC).  
7.  
Information Items  
Contract 59-25 was awarded to Vinton Construction Company for  
$1,370,111.56 with a contingency of $205,516.00 for WWTP Hardscape.  
Change orders were approved totaling $106,987.72. Final contract amount is  
$1,477,099.28 with a contingency of $98,528.28. Payments issued to date total  
$1,270,146.89. Request final payment of $206,952.39.  
Contract 21-24 was awarded to Peters Concrete Company for Unit H-23  
Lightning Drive Extension Phase 1 for $1,544,853.12 with a contingency of  
$116,000. Three Change Orders have been approved in the amount of  
$265,960.36. Final contract amount is $1,810,813.48. Payments issued to  
date total $1,436,806.26. Request Final payment of $228,657.07.  
Contract 30-25 was awarded to Kruczek Construction for Unit U-25 Sewer &  
Water Reconstruction for $2,525,555.55 with a contingency of $70,000.00.  
Payments issued to date total $2,351,766.42. Request Final payment of  
$156,012.33.  
Contract 37-25 was awarded to Vinton Construction for Unit B-25 Asphalt  
Pavement Reconstruction for $1,285,258.51 with a contingency of $41,000.00.  
One Change Order was approved in the amount of $57,830.90. Final contract  
amount is $1,343,089.41. Payments issued to date total $1,211,671.86.  
Request Final payment of $131,417.42  
8.  
Adjournment  
Notice is hereby given that a quorum of the Common Council may be present during this  
meeting, although no Council action will be taken.  
Reasonable Accommodations for Persons with Disabilities will be made upon Request  
and if Feasible.