Request to approve Contract Amendment #1 to Donohue as part of the
AWWTP Anaerobic Digester Inspection, Maintenance, and Improvements
Project to support Phase 5 Construction Services in the amount of $209,479
increasing the contract amount from $293,755 to $503,234 along with the
following 2025-2026 Budget carryover appropriations (2/3 vote of Council
required):
Wastewater Utility Fund
2025 Digester Cathodic Protection & Corrosion Control
2025 Equipment Repairs & Maintenance
2026 Digester Cathodic Protection & Corrosion Control
2026 Equipment Repairs & Maintenance
- $316,200
- $187,034
+ $316,200
+ $187,034
Attachments:
Request to award the Alicia Playground Equipment Project contract to Lee
Recreation LLC in an amount not to exceed $130,000.
Attachments:
Request to award Unit B-26 Asphalt Paving to Triple P Inc. dba Peters
Concrete Company in the amount of $1,244,583.86 with a 3.6% contingency of
$45,000 for a project total not to exceed $1,289,583.86.
Attachments:
Request to award sole source purchase of Rockwell Automation/Allen Bradley
Variable Frequency Drive equipment to Werner Electric in the amount of
$203,197.
Attachments:
7.
Information Items
Facilities and Construction Management 2025 Annual Review.
Attachments:
Change Orders #9 through #12 to Staab Construction contract as part of the
AWWTP Phase 2 Belt Filter Press Equipment Upgrades Project totaling
$147,164 resulting in a decrease in contingency from $530,312 to $383,130.
Contract 68-24 was awarded to August Winter & Sons for $242,000 with a
contingency of $48,400 for Water Treatment Facility Clearwell Repairs.
Change orders were approved totaling $4,679. Final contract amount is
$246,679 with a contingency of $43,721. Payments issued to date total
$240,512.03. Request final payment of $6,166.97.
8.
Adjournment
Notice is hereby given that a quorum of the Common Council may be present during
this meeting, although no Council action will be taken.
Reasonable Accommodations for Persons with Disabilities will be made upon Request
and if Feasible.