22-0190
| 1 | | | Minutes | Minutes from February 7, 2022 | approved | Pass |
Action details
|
Video
|
22-0191
| 1 | | | Report Action Item | Approve Plan Review Services Contract for Large Projects to E-Plan Exam. | recommended for approval | Pass |
Action details
|
Video
|
22-0192
| 1 | | | Report Action Item | Approve proposed change to Municipal Code Section 19-112, Non-metered off-street parking. | recommended for approval | Pass |
Action details
|
Video
|
22-0193
| 1 | | | Report Action Item | Approve modifications to the Downtown Parking Policy for City Employees. | recommended for approval | Pass |
Action details
|
Video
|
22-0194
| 1 | | | Report Action Item | Request to replace hotel signage on the College Avenue Skywalk with sign for Vince Lombardi's Steakhouse. | recommended for approval | Pass |
Action details
|
Video
|
22-0195
| 1 | | | Report Action Item | Request from Greenfire for a street occupancy permit for a crane and construction staging area to extend 30 feet into the Oneida Street right-of-way at 103 W. College Avenue through December 31, 2022. | recommended for approval | Pass |
Action details
|
Video
|
22-0200
| 1 | | | Report Action Item | Request from James Johnston to appeal his $75 non-compliance fee for a tire collected at 1130 E. Sunset Avenue. | recommended for denial | Pass |
Action details
|
Video
|
22-0201
| 1 | | | Report Action Item | Approve parking restriction change on the 800 block of W. Eighth Street (Badger Avenue to Pierce Avenue). Follow-up to six-month trial period. | recommended for approval | Pass |
Action details
|
Video
|
22-0202
| 1 | | | Report Action Item | Approve parking restriction change on the 100 block of W. College Avenue adjacent to Houdini Plaza. Follow-up to six-month trial period. | recommended for approval | Pass |
Action details
|
Video
|
22-0203
| 1 | | | Report Action Item | Approve installation of STOP signs on Locust Street at Oklahoma Street. Follow-up to six-month trial period. | recommended for approval | Pass |
Action details
|
Video
|
22-0212
| 1 | | | Report Action Item | Preliminary Resolution 1-P-22 for Concrete Pavement, Driveway Aprons and Sidewalk Construction be adopted and refer the matter to the Finance Committee to determine the assessment rate. | recommended for approval | Pass |
Action details
|
Video
|
22-0213
| 1 | | | Report Action Item | Resolution #3-R-22 regarding Municipal Code Chapter 12, Article III, Weeds and Wild Growth. | held | Pass |
Action details
|
Video
|
22-0204
| 1 | | | Report Action Item | Discussion of desired process for possible redesign of Soldier Square per Resolution #5-R-19. | | |
Action details
|
Video
|
22-0210
| 1 | | | Report Action Item | Review Crosswalk Installation Evaluation Guidance Flowchart. | | |
Action details
|
Video
|
22-0211
| 1 | | | Report Action Item | Update on Transportation Utility Funding Study. | | |
Action details
|
Video
|