18-0118
| 1 | | | Minutes | Finance Committee minutes for January 8, 2018 and January 15, 2018 | approved | Pass |
Action details
|
Video
|
18-0048
| 1 | | | Report Action Item | Request to approve Rocky Bleier Run/Water Street Relocation Order (north side of street). | confirmed | Pass |
Action details
|
Video
|
18-0119
| 1 | | | Report Action Item | Request to award Unit T-18 Telulah Avenue Sewer & Water Main Reconstruction No. 1 to Kruczek Construction, Inc in the amount of $1,477,778 with a 5% contingency of $73,889 for a project total not to exceed $1,551,667. | recommended for approval | Pass |
Action details
|
Video
|
18-0120
| 1 | | | Report Action Item | Request to approve Finance Committee Report 1-P-18 for Sanitary Laterals | recommended for approval | Pass |
Action details
|
Video
|
18-0126
| 1 | | | Report Action Item | Request to apply for the FEMA FY17 Assistance to Firefighter's Grant for personal protective equipment | recommended for approval | Pass |
Action details
|
Video
|
18-0128
| 1 | | | Report Action Item | Resolution introduced by Alderperson Baranowski at January 17, 2018 Common Council meeting relating to short-term loan to Appleton Redevelopment Authority for the construction of the Fox Cities Exhibition Center.
Resolution #1-R-18
Submitted by: Alderperson Baranowski - District 5
Whereas, the City of Appleton approved a short-term loan not to exceed $31,000,000 to the Appleton Redevelopment Authority (ARA) for the construction of the Fox Cities Exhibition Center and,
Whereas, the short-term loan is to be repaid upon ARA's closing of long-term financing for the project and,
Whereas an estimate of the amount of interest income not received due to the amounts paid to fund the Fox Cities Exhibition Center, projecting through March 1, 2018, would be approximately $237,500 therefore,
Be it resolved, the City of Appleton is repaid from the hotel room tax fund, upon ARA’s closing of long-term financing for the project, any and all interest income it would have earned on the funds the City loaned to ARA for the Fox Cities Exhibition Center project. | recommended for approval | Pass |
Action details
|
Video
|
18-0121
| 1 | | | Presentation | Contract 50-16 was awarded to Miron Construction for the 2016 Erb Park and Pool Renovation project in the amount of $8,757,842 with a contingency of $613,048. Change orders totaled $267,983, leaving a contingency balance of $345,065. Request to issue the final contract payment of $17,006.77 | received and filed | |
Action details
|
Video
|
18-0122
| 1 | | | Presentation | Contract 55-17 was awarded to VOE Power and Systems, LLC for the 2017 MSB Fire Alarm project in the amount of $68,177 with a contingency of $10,000. One change order was issued in the amount of $773. Payments issued to date totaled $65,502. Request to issue the final contract payment of $3,447.48 | received and filed | |
Action details
|
Not available
|
18-0123
| 1 | | | Presentation | Contract 69-17 was awarded to Bodart Electric Company, Inc for the 2017 Parks Lighting Upgrades project in the amount of $70,894 with a contingency of 10%. One change order was issued in the amount of $3,500. No payments have been made. Request to issue the final contract payment of $74,393.65 | received and filed | |
Action details
|
Not available
|
18-0124
| 1 | | | Presentation | Contract 54-17 was awarded to VOE Power and Systems, LLC for the 2017 Wastewater Lighting Upgrade project in the amount of $41,740 with a contingency of $10,000. One change order was issued in the amount of $5,723. Payments issued to date totaled $45,090. Request to issue the final contract payment of $2,373.17 | received and filed | |
Action details
|
Not available
|
18-0125
| 1 | | | Presentation | Request to add Sanitary Sewer and Storm Sewer construction on Durkee Street between Atlantic Street and Summer Street to our 2018 Reconstruction Program (action item on Utilities Committee agenda) | received and filed | |
Action details
|
Not available
|
18-0127
| 1 | | | Presentation | Director's Reports:
Finance
- Staffing Update
- ERP Project
Legal Services
No Report
Parks, Recreation & Facilities Management
- Facilities Management Project Updates | received and filed | |
Action details
|
Video
|
18-0130
| 1 | | | Presentation | The following 2017 Budget adjustments were approved by the Mayor and Finance Director in accordance with Policy:
General Fund - Library
Other Contracts/Obligations - Administration +$47,000
Books & Library Materials - Materials Management - $47,000
to transfer funds to fund the cost of safety and security services | received and filed | |