Meeting Name: Municipal Services Committee Agenda status: Final
Meeting date/time: 10/23/2017 4:30 PM Minutes status: Final  
Meeting location: Council Chambers, 6th Floor
Published agenda: Agenda Agenda Published minutes: Minutes Minutes  
Meeting video:  
Attachments: MSC Agenda Packet 10-23-17.pdf
File #Ver.Agenda #NameTypeTitleActionResultAction DetailsVideo
17-1605 1  Report Action ItemMinutes from October 9, 2017approvedPass Action details Video Video
17-1672 1  Report Action ItemDesign Hearing for the following streets in the 2019 pavement reconstruction program: a. Alvin Street from Evergreen Drive to cul-de-sac b. Evergreen Drive from Alvin Street to Haymeadow Avenue   Action details Video Video
17-1606 1  Report Action ItemSummit Street, from Spencer Street to College Avenue, be reconstructed with asphalt pavement and concrete curb and gutter to a width of 31’ from back of curb to back of curb, which is 2’ narrower than the existing street. A new splitter island will be reconstructed at the south end of Summit Street, located at the intersection with Spencer Street and the railroad crossing. The proposed splitter island will restrict left turns from Summit Street on to Spencer Street in an effort to improve the safety at the railroad crossing, and is a part of the city-wide quiet zone implementation for all railroad crossings. Existing on-street parking provisions within the project limits will remain unchanged.recommended for approvalPass Action details Video Video
17-1674 1  Report Action ItemDurkee Street, from Atlantic Street to Summer Street, be reconstructed with asphalt pavement and concrete curb and gutter to a width of 31’ from back of curb to back of curb, which is 2’ narrower than the existing street. Existing on-street parking provisions within the project limits will remain unchanged.recommended for approvalPass Action details Video Video
17-1678 1  Report Action ItemHall Avenue, from Woodland Avenue to Grant Street, be reconstructed with asphalt pavement and concrete curb and gutter to a width of 31’ from back of curb to back of curb, which is 2’ narrower than the existing street. New concrete sidewalk would be constructed along the east side of Hall Avenue within the project limits. Existing on-street parking provisions within the project limits will remain unchanged.recommended for approvalPass Action details Video Video
17-1607 1  Report Action ItemRequest from Raymond and Claudine Green, 1400 E. Capitol Drive, for a variance to Municipal Code 19-91(f)(5) to extend his driveway 16 feet into the front yard.recommended for approvalPass Action details Video Video
17-1608 1  Report Action ItemApprove revised State/Municipal Agreement for the US 10/Oneida Street Interchange Project to include intelligent transportation system installations for a revised total Municipal Fund share of $34,463.recommended for approvalPass Action details Video Video
17-1609 1  Report Action ItemRequest from John Houlihan and Nancy Mills, 17 Riverfront Court, to appeal the denial for a second driveway to Pierce Court.recommended for approvalPass Action details Video Video
17-1610 1  Report Action ItemRequest from the Radisson Paper Valley Hotel to convert the 4 metered stalls in the 300 W Lawrence Street block (planned to be installed as part of the Lawrence Street reconstruction project) to a 10-minute loading zone.recommended for approvalPass Action details Video Video
17-1611 1  Report Action ItemRequest by staff to have two properties (tax key 1-9300-53 and tax key 1-9300-38) officially precluded from access to Canyon Lane.recommended for approvalPass Action details Video Video
17-1669 1  Report Action ItemAward 5-Year (2018-2022) Neglected Sidewalk Snow Shoveling Services to Special Forces Building and Grounds, LLC.recommended for approvalPass Action details Video Video
17-1681 1  Report Action ItemApprove Contract Amendment/Change Order No. 1 to contract 64-17 for Red Ramp Structural Repairs to increase for the repair of an additional 95 square feet of deteriorated structural concrete beam, identified at time of adjacent column repairs in the amount of $22,705.00 resulting in a decrease to contingency from $5,292.00 to $0.00. Overall contract increased from $40,572.00 to $57,985.00.recommended for approvalPass Action details Video Video
17-1667 1  Report Action ItemInspections Division Permit Summary Comparison Report for September, 2017.   Action details Not available
17-1668 1  Report Action ItemDiscussion of 2018 Executive Budget.   Action details Not available