Meeting Name: Finance Committee Agenda status: Final
Meeting date/time: 11/6/2023 5:30 PM Minutes status: Final  
Meeting location: Council Chambers, 6th Floor
Published agenda: Agenda Agenda Published minutes: Minutes Minutes  
Meeting video:  
Attachments: FC Agenda Packet 11-6-23.pdf
File #Ver.Agenda #NameTypeTitleActionResultAction DetailsVideo
23-1345 1  Minutes10/23/23 Meeting MinutesapprovedPass Action details Video Video
23-1346 1  Report Action ItemRequest to award Health Department Furniture Remodel to Nordon Business Environments in the amount of $250,887.34.recommended for approvalPass Action details Video Video
23-1358 1  Report Action ItemRequest to accept 2022 WIPPI Energy Efficiency Grant in the amount of $72,564 for the Appleton Water Treatment Plant Kathabar Replacement Project.recommended for approvalPass Action details Video Video
23-1347 1  PresentationContract 120-22 was awarded to RJM Construction, LLC. for the 2022 AWWTP F1 Building Renovation Project in the amount of $271,840 with a 15% contingency of $40,776. Three change orders were issued in the amount of $12,505. Payments to date total $264,974. Request to issue the final contract payment of $19,371.received and filed  Action details Video Video
23-1348 1  PresentationContract 115-22 was awarded to RJM Construction, LLC. for the 2022 Telulah Pavilion Renovation Project in the amount of $160,322 with a 12% contingency of $19,239. Three change orders were issued in the amount of $31,686. Payments to date total $138,045.67. Request to issue the final contract payment of $53,912.24received and filed  Action details Not available
23-1349 1  PresentationContract 32-23 was awarded to Northeast Asphalt, Inc. for the 2023 Water Plant Hardscapes Project in the amount of $522,443 with a 15% contingency of $78,336. Four change orders were issued in the amount of $60,330. Payments to date total $524,495.81. Request to issue the final contract payment of $58,277.31.received and filed  Action details Not available
23-1350 1  PresentationChange Order #2 to Staab Construction contract as part of the AWWTP Phase I Belt Filter Press Equipment Upgrades Project totaling $6,625 resulting in a decrease in contingency from $782,175 to $775,550.received and filed  Action details Not available
23-1359 1  PresentationContract 152-21 was awarded to Carl Bowers & Sons Construction for Sequoia Drive Sewer, Water and Grade & Gravel Construction in the amount of $801,025 with a 5% contingency of $40,000. Payments to date total $745,209.09. Request to issue the final contract payment of $46,209.98.received and filed  Action details Not available