| 20-1425 | 1 |  |  | Minutes | Minutes from October 12, 2020 | recommended for approval | Pass | Action details | Not available | 
							| 20-1426 | 1 |  |  | Report Action Item | Meade Street, from Pacific Street to Commercial Street, be reconstructed with concrete pavement and curb and gutter.  The dimensions of the Meade Street reconstruction project are as follows:
Pacific St - Hancock St:  New concrete pavement to be constructed to a width of 33’ from back of curb to back of curb, which is the same width as the existing street within this portion of the project.  On-street parking would be restricted along the east side of Meade Street within this portion of the project.
Hancock St - Commercial St:  New concrete pavement to be constructed to a width of 43’ from back of curb to back of curb, which is the same width as the existing street within this portion of the project.  Existing on-street parking to remain unchanged within this portion of the project. | recommended for approval | Pass | Action details | Not available | 
							| 20-1430 | 1 |  |  | Report Action Item | Kimball Alley, from Mason Street to Story Street, be reconstructed with concrete pavement.  The dimensions of the Kimball Alley reconstruction project are as follows:
Mason St - Spruce St:  New concrete pavement to be constructed to a width of 16’ from edge of pavement to edge of pavement, which is the same width as the existing alley within this portion of the project.  
Spruce St - Summit St:  New concrete pavement to be constructed to a width of 14’ from edge of pavement to edge of pavement, which is the same width as the existing alley within this portion of the project.  
Summit St - Story St:  New concrete pavement to be constructed to a width of 20’ from edge of pavement to edge of pavement, which is the same width as the existing alley within this portion of the project. | recommended for approval | Pass | Action details | Not available | 
							| 20-1431 | 1 |  |  | Report Action Item | Kimball Alley, from Walnut Street to Lawrence Street, be reconstructed with concrete pavement to a width of 20’ from edge of pavement to edge of pavement, which is the same width as the existing alley. | recommended for approval | Pass | Action details | Not available |