14-1616
| 1 | | | Minutes | Approval of the September 9, 2014 Utilities Committee Meeting minutes. | approved | Pass |
Action details
|
Video
|
14-1670
| 1 | | | Minutes | Approval of the September 24, 2014 Joint Utilities and Park and Recreation Meeting minutes. | approved | Pass |
Action details
|
Video
|
14-1672
| 1 | | | Report Action Item | Award Replacement and Repair of doors at Wastewater Plant to Tri-City Glass and Door in the amount of $28,692 with a contingency of $1,308 for a project total not to exceed $30,000. | recommended for approval | Pass |
Action details
|
Video
|
14-1689
| 1 | | | Report Action Item | Approve Contract Amendment #1 for the AWWTP Evaluation of Phosphorous Treatment Optimization and TMDL Compliance Project to CH2M Hill for additional consulting services in the amount of $15,285 resulting in a decrease in contingency from $15,285 to $0. | recommended for approval | Pass |
Action details
|
Video
|
14-1671
| 1 | | | Presentation | Issued contract to Martenson & Eisele, Inc. in the amount of $6,413 for engineering services for the recoating of roofs at the Wastewater Treatment Plant. | | |
Action details
|
Video
|
14-1725
| 1 | | | Presentation | Reid Golf Course Storm Water Project has been selected to receive a 2014 ASGCA Design Excellence Recognition award. | | |
Action details
|
Video
|
14-1617
| 1 | | | Presentation | Monthly Reports for August 2014
- Water Distribution and Meter Team Monthly Report | | |
Action details
|
Video
|