23-0273
| 1 | | | Minutes | Approval of the March 7, 2023 Utilities Committee Meeting minutes. | approved | Pass |
Action details
|
Video
|
23-0291
| 1 | | | Report Action Item | Award Unit R-23 Chemical Root Foaming of Sanitary Sewers to Duke's Root Control, Inc. in an amount not to exceed $25,000. | recommended for approval | Pass |
Action details
|
Video
|
23-0304
| 1 | | | Report Action Item | Award purchase of Primary Digester Circulation Pump from Crane Engineering in the amount of $27,774. | recommended for approval | Pass |
Action details
|
Video
|
23-0300
| 1 | | | Report Action Item | Award the Sole Source Purchase of Secondary Clarifier Algae Sweep System from Ford Hall Company, Inc., in the amount of $131,040 with a 15% contingency of $19,656 for a project total not to exceed $150,696. | recommended for approval | Pass |
Action details
|
Video
|
23-0301
| 1 | | | Report Action Item | Sole Source Engineering Services Contract to McMahon as part of Phase II Belt Filter Press Equipment Upgrades Project in the amount of $162,000 with a 15% contingency of $24,300 for a Project Total not to exceed $186,300. | recommended for approval | Pass |
Action details
|
Video
|
23-0302
| 1 | | | Report Action Item | Sole Source Engineering Services Contract to McMahon as part of the 2023 Digester Piping and Heat Exchanger Replacement Project in the amount of $85,300 with a 15% contingency of $12,795 for a Project Total not to exceed $98,095. | recommended for approval | Pass |
Action details
|
Video
|
23-0297
| 1 | | | Presentation | Monthly Report for February 2023:
- Water Distribution and Meter Team Monthly Report | | |
Action details
|
Video
|