Meeting Name: Finance Committee Agenda status: Final
Meeting date/time: 1/8/2024 5:30 PM Minutes status: Final  
Meeting location: Council Chambers, 6th Floor
Published agenda: Agenda Agenda Published minutes: Minutes Minutes  
Meeting video:  
Attachments: FC Agenda Packet 1-8-24.pdf
File #Ver.Agenda #NameTypeTitleActionResultAction DetailsVideo
23-1528 1  Minutes12/11/23 Finance Committee Meeting MinutesapprovedPass Action details Video Video
24-0001 1  Report Action ItemRequest to award the City of Appleton's Library Signage Package contract to Seating Concepts Inc., in the amount of $185,994.61 with a 5% contingency of $10,000 for a project total not to exceed $195,994.61.recommended for approvalPass Action details Video Video
24-0002 2  Report Action ItemRequest to award the Engineering Contract for the 2023 AWWTP L-Building HVAC Replacement Project to McMahon in the amount of $156,898 with a 5% contingency of $7,845 for a total not to exceed project engineering cost of $164,743.recommended for approvalPass Action details Video Video
24-0003 1  Report Action ItemRequest to award the 2023 AWWTP B-Building HVAC Upgrades Project contract to Rohde Brothers, Inc. in the amount of $720,840 with a 9% contingency of $64,876 for a project total not to exceed $785,716, along with the following budget amendment (2/3 vote of Council required): AWWTP Electrical Distribution Project - $54,000 AWWTP HVAC Upgrades Project +$54,000recommended for approvalPass Action details Not available
24-0004 1  Report Action ItemRequest to award the Engineering Contract for the AWWTP MCC Replacement Project Phase 1 to Donohue and Associates in the amount of $159,420 for data collection and bidding documents along with $124,719 for bidding and construction oversight services upon approval of funding in the 2025 budget as this is a multiyear project, for a total contract amount of $284,139, along with the following 2023 budget amendment (2/3 vote of Council required): AWWTP Electrical Distribution Project -$60,000 2023 AWWTP MCC Replacement Project +$60,000recommended for approvalPass Action details Video Video
24-0005 1  Report Action ItemRequest to approve the Relocation Order for work at or near 1850 West Wisconsin Avenue.recommended for approvalPass Action details Video Video
24-0012 1  Report Action ItemRequest to approve write off of $74,881.54 of accounts receivable invoices and $16,668.36 of personal property taxes (outstanding over one year).recommended for approvalPass Action details Video Video
24-0013 1  Report Action ItemRequest to approve Change Order #4 to contract 72-22 for Unit H-21 Redundant Raw Water Line to increase for unanticipated site conditions in the amount of $176,232.54 resulting in a decrease in contingency from $244,549.71 to $0.00. No change to overall contract amount.recommended for approvalPass Action details Video Video
24-0014 1  Report Action ItemRequest to award Unit H-23 Lightning Drive Sewer & Water, Grade & Gravel, and Bridge Construction to Triple P Inc., dba Peters Concrete Company, in the amount of $1,544,853.12 with a 7.5% contingency of $116,000.00 for a project total not to exceed $1,660,853.12.recommended for approvalPass Action details Video Video
24-0015 1  Report Action ItemRequest to award a sole source contract to McMahon for design, bidding, and construction oversite for the 2024 Wastewater Hardscapes Improvement Project, for a contract fee of $56,600 and a 5% contingency of $2,830 not to exceed a total contract amount of $59,430.recommended for approvalPass Action details Video Video
24-0016 1  Report Action ItemRequest to award a sole source contract to Nordon Business Environments for the Municipal Services Building Furniture Upgrades in the amount of $189,135.72.recommended for approvalPass Action details Video Video
24-0017 1  PresentationContract 35-23 was awarded to Scott Lamers Construction LLC for $400,910 with a contingency of $99,090 for Y-23 Lead/Galvanized Water Service Replacement. Change orders were approved totaling $74,193.13. Final contract amount is $475,103.13 with a contingency of $24,896.87. Payments issued to date total $345,594.75. Request final payment of $129,508.38.received and filed  Action details Not available
24-0018 1  PresentationContract 124-22 was awarded to Rohde Brothers for $223,900 with a contingency of $26,868 for WW F-1 Bldg HVAC. Change orders were approved totaling $5,447. Final contract amount is $229,347 with a contingency of $21,421. Payments issued to date total $198,222.50. Request final payment of $31,124.50.received and filed  Action details Not available
24-0019 1  PresentationContract 43-23 was awarded to Vinton Construction for $684,731.28 with a contingency of $27,000 for Asphalt Pavement Reconstruction. Payments issued to date total $492,066.24. Request final payment of $55,967.58.received and filed  Action details Not available
24-0020 1  PresentationContract 56-21 was awarded to ASTI Sawing for $30,000 for Concrete Sidewalk Sawcutting. Payments issued to date total $13,226.11. Request final payment of $16,773.89.received and filed  Action details Not available
24-0021 1  PresentationContract 65-23 was awarded to Kruczek Construction for $1,044,444 with a contingency of $52,222 for X-23 Water Reconstruction No. 2. Payments issued to date total $682,990.45. Request final payment of $135,520.83.received and filed  Action details Not available
24-0022 1  PresentationContract 41-23 was awarded to Vinton Construction Company for $499,980.65 with a contingency of $60,000 for WW Hardscape 2023. Change orders were approved totaling $7,977.55. Final contract amount is $507,958.20 with a contingency of $52,022.45. Payments issued to date total $446,020.61. Request final payment of $61,937.59.received and filed  Action details Not available
24-0023 1  PresentationContract 54-23 was awarded to M & E Construction, LLC for $200,000 for Mini Storm Sewer Construction. No payments issued to date. Request final payment of $199,925.received and filed  Action details Not available
24-0024 1  PresentationContract 52-22 was awarded to Triple P Inc. dba Peters Concrete Company for the 2022 Ellen Kort Peace Park River Trail Project in the amount of $464,131.41 with a contingency of $46,413. Four change orders were approved totaling $45,146.69. Payments issued to date total $504,278.10. Request to issue the final payment of $5,000.00.received and filed  Action details Not available
24-0033 1  PresentationChange Orders #9, #10, and #11 to Miron Construction contract as part of the AWWTP Sludge Storage Building Addition Construction Project totaling $19,646 resulting in a decrease in contingency from $552,192 to $532,546.received and filed  Action details Not available
24-0037 1  PresentationThe following 2023 Budget adjustments were approved by the Finance Director in accordance with Policy: General Fund - Library Children's Services - Other Reimbursements +$100 Children's Services - Office Supplies ELL +$100 Building for Kids General Fund - Library Materials Management - Other Reimbursements +$50 Materials Management - Books & Library Materials +$50 John C. Roberts Donation for Materials General Fund - Library Children's Services - Food & Provisions ELL +$3,359 Children's Services - Office Supplies ELL - $3,359 Move ELL funds to supply line as requested by AC General Fund - Library Materials Management - Other Reimbursement +$50 Materials Management - Books & Library Materials +$50 Cookie Fielkow Donation for Materials General Fund - Library Library Admin - Donation +$50 Materials Management - Book & Library Materials +$50 Donation for purchase of collection materials General Fund - Library Community Partnerships - Other Reimbursements +$5,000 Community Partnerships - Part Time Wages +$5,000 Libraries in Bloom General Fund - received and filed  Action details Not available
24-0038 1  PresentationThe following 2023 Budget adjustment was approved by the Mayor and Finance Director in accordance with Policy: General Fund - CED Miscellaneous Revenue +$950 Training/Conferences +$950 Travel Stipend received from Smart Growth America for trainingreceived and filed  Action details Not available