15-936
| 1 | | Minutes of the 5-26-15 Utilities Committee Meeting | Minutes | Minutes of the 5-26-15 Utilities Committee Meeting | approved | Pass |
Action details
|
Not available
|
15-954
| 1 | | Memo for Preliminary Resolution 3-P-15 | Report Action Item | Preliminary Resolution 3-P-15 for Sanitary Sewer, Storm Sewer, Sanitary Laterals & Storm Laterals be adopted and refer the matter to the Finance Committee to determine the assessment rate. | recommended for approval | Pass |
Action details
|
Not available
|
15-962
| 1 | | 2015 W. Wisconsin Flood Reduction Project Memo | Report Action Item | Request from the Department of Public Works to postpone the proposed 2015 West Wisconsin Flood Reduction Project - Phase 2A due to soil related/regulatory permitting issues and re-budget in a future year. | recommended for approval | Pass |
Action details
|
Not available
|
15-937
| 1 | | Stormwater Projects Update by DPW Staff | Presentation | Stormwater Projects Update by DPW Staff | | |
Action details
|
Not available
|