| 22-1277 | 1 |  |  | Minutes | 9/26/22 Finance Committee Minutes | approved | Pass | Action details |  Video | 
							| 22-1278 | 1 |  |  | Report Action Item | Request to reject base bid from Staab Construction in the amount of $643,600 for the 2022 AWWTP Blended Sludge Piping and Preliminary Heat Exchanger Replacement Project. | recommended for approval | Pass | Action details |  Video | 
							| 22-1282 | 1 |  |  | Report Action Item | Request to award the 2022 AWWTP Biogas Boiler System Upgrades Project contract to Rohde Brothers, Inc. in the amount of $333,450 with a 12% contingency of $40,014 for a project total not to exceed $373,464. | recommended for approval | Pass | Action details |  Video | 
							| 22-1283 | 1 |  |  | Report Action Item | Request to award the City of Appleton’s 2022 Telulah Pavilion Repairs Project contract to RJM Construction, LLC. in the amount of $158,572 with a 12% contingency of $19,028 for a project total not to exceed $177,600. | recommended for approval | Pass | Action details | Not available | 
							| 22-1284 | 1 |  |  | Report Action Item | Request to award the City of Appleton’s 2022 AWWTP Painting Project contract to SDS Painting Co., Inc. in the amount of $121,760 with a 8% contingency of $10,000 for a project total not to exceed $131,760. | recommended for approval | Pass | Action details |  Video | 
							| 22-1288 | 1 |  |  | Report Action Item | Request to approve the following 2022 Budget amendment: 
Public Works Capital Project Fund		-$27,302
Facilities Capital Project Fund	           +$27,302
To record transfer of sidewalk costs from Public Works Capital Project Fund to Facilities Capital Project Fund. | recommended for approval | Pass | Action details |  Video | 
							| 22-1289 | 1 |  |  | Presentation | Change Orders #8 and #9 to Staab Construction contract as part of the 2019 AWWTP Improvements Projects totaling $24,320 resulting in a decrease in contingency from $159,231 to $134,911. |  |  | Action details | Not available | 
							| 22-1290 | 1 |  |  | Presentation | Contract 149-20 was awarded to B&P Mechanical Inc. for $93,976 with a contingency of $9,398 for WWTP D-Bldg HVAC.  Change orders were approved totaling $7,955.34.  Final contract amount is $101,931.34 with a contingency of $1,442.66.  Payments issued to date total $92,297.25.  Request final payment of $9,634.09. |  |  | Action details | Not available | 
							| 22-1304 | 1 |  |  | Presentation | A 2022 Budget adjustment was approved by the Mayor and Finance Director in accordance with Policy for:
Reid Golf Course
Donations			+$1,260
Supplies			+$1,260
To record donation for bench at Golf Course. |  |  | Action details | Not available | 
							| 22-1303 | 1 |  |  | Presentation | A 2022 Budget adjustment was approved by the Mayor and Finance Director in accordance with Policy for:
General Fund - Recreation
Donations			+$4,850
Supplies			+$4,850
To record donations from Jacobson/Thiel/Weyenberg/Vanderheiden families for various parks and trails. |  |  | Action details | Not available | 
							| 22-1302 | 1 |  |  | Presentation | A 2022 Budget adjustment was approved by the Mayor and Finance Director in accordance with Policy for:
General Fund - Library
Reimbursements			+$10,000
Other Contracts			+$10,000
To record grant funds received from the City of Racine for CLC. |  |  | Action details | Not available | 
							| 22-1301 | 1 |  |  | Presentation | A 2022 Budget adjustment was approved by the Mayor and Finance Director in accordance with Policy for:
General Fund - Library
Reimbursements			+$4,871
Supplies			            +$4,871
To record funds received from Northern Waters Library Service and United Way. |  |  | Action details | Not available |