File #: 22-0736    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 5/25/2022 In control: Utilities Committee
On agenda: 6/7/2022 Final action: 6/15/2022
Title: Award 2022 AWWTP Preliminary Heat Exchanger and Blended Sludge Piping Replacement Project Engineering Services Amendment #1 increasing the McMahon total contract amount by $3,800 from $26,300 to $30,100 and increase contingency from $2,630 to $4,000 for a Project Total not to exceed $34,100.
Attachments: 1. Contract Amend #1_McMahon_2022 AWWTP Prelim HEX-Blended Sludge Piping.pdf

Title

Award 2022 AWWTP Preliminary Heat Exchanger and Blended Sludge Piping Replacement Project Engineering Services Amendment #1 increasing the McMahon total contract amount by $3,800 from $26,300 to $30,100 and increase contingency from $2,630 to $4,000 for a Project Total not to exceed $34,100.