Title: Change Order No. 3 to Staab Construction for the DAF Conversion to Receiving Tank Project in the amount of $10,495 for the replacement of tank carbon steel header to stainless steel resulting in a decrease of contingency from $13,115 to $2,620
Attachments: 1. Change Order 3 DAF to Receiving Station 05-10-22.pdf

Title

Change Order No. 3 to Staab Construction for the DAF Conversion to Receiving Tank Project in the amount of $10,495 for the replacement of tank carbon steel header to stainless steel resulting in a decrease of contingency from $13,115 to $2,620