File #: 21-1777    Version: 1 Name:
Type: Presentation Status: Filed
File created: 1/6/2022 In control: Finance Committee
On agenda: 1/10/2022 Final action: 1/10/2022
Title: Change Order No. 1 to contract 133-21, Unit U-21 Apple Creek Court & Plamann Park Sewer and Water Construction, for an additional 20 feet of augered 30" concrete casing pipe under stormwater channel in Plamann Park in the amount of $23,400.00. This change order reduces contingency from $100,000.00 to $76,600.00. Overall contract amount remains unchanged
Attachments: 1. Unit U-21 Change Order No. 1.pdf

Title

Change Order No. 1 to contract 133-21, Unit U-21 Apple Creek Court & Plamann Park Sewer and Water Construction, for an additional 20 feet of augered 30" concrete casing pipe under stormwater channel in Plamann Park in the amount of $23,400.00.  This change order reduces contingency from $100,000.00 to $76,600.00.  Overall contract amount remains unchanged