File #: 21-1776    Version: 1 Name:
Type: Presentation Status: Filed
File created: 1/6/2022 In control: Finance Committee
On agenda: 1/10/2022 Final action: 1/10/2022
Title: Change Order No. 2 to contract 76-21, Unit L-21 Sewer and Water Construction - Lightning and Edgewood, for unanticipated subsurface obstructions encountered during trenchless sewer and water casing installations in the amount of $8,000.00. This change order reduces contingency from $44,475.00 to $36,475.00. Overall contract amount remains unchanged.
Attachments: 1. Unit L-21 Change Order No. 2.pdf

Title

Change Order No. 2 to contract 76-21,  Unit L-21 Sewer and Water Construction - Lightning and Edgewood, for unanticipated subsurface obstructions encountered during trenchless sewer and water casing installations in the amount of $8,000.00.  This change order reduces contingency from $44,475.00 to $36,475.00.  Overall contract amount remains unchanged.