Title: Contract 21-20 was awarded to Janke General Contractors for the 2020 Lawe Street Trestle Trail Project in the amount of $1,305,205 with a contingency of $130,521. Three change orders were issued in the amount of $24,474 to remove additional railroad track, repair girders and abutments, and add rip rap. Payments to date total $1,319,679.57. Request to issue the final contract payment of $10,000.

Title

Contract 21-20 was awarded to Janke General Contractors for the 2020 Lawe Street Trestle Trail Project in the amount of $1,305,205 with a contingency of $130,521. Three change orders were issued in the amount of $24,474 to remove additional railroad track, repair girders and abutments, and add rip rap. Payments to date total $1,319,679.57. Request to issue the final contract payment of $10,000.