Title:
|
Contract 42-21 was awarded to Northeast Asphalt, Inc. for the 2021 Parks Hardscapes Project - AMP Parking Lot #3 Reconstruction Project in the amount of $289,788.02 with a contingency of $60,947.45. One change order was issued in the amount of $60,947.45 to add additional Engineered Base Stabilizer (EBS) and drain tile. Payments to date total $333,198.70. Request to issue the final contract payment of $17,536.77.
|