File #: 21-0502    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 4/21/2021 In control: Finance Committee
On agenda: 4/26/2021 Final action: 4/26/2021
Title: Contract 7-20 was awarded to Milbach Construction for the 2019 DPW Remodel Project in the amount of $605,630 with a contingency of $35,000. Change orders totaled $23,894. The scope was increased to provide data cabling. Payments to date total $566,572.04. Request to issue the final contract payment of $62,952.45

Title

Contract 7-20 was awarded to Milbach Construction for the 2019 DPW Remodel Project in the amount of $605,630 with a contingency of $35,000. Change orders totaled $23,894. The scope was increased to provide data cabling. Payments to date total $566,572.04. Request to issue the final contract payment of $62,952.45