File #: 20-1432    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 10/21/2020 In control: Finance Committee
On agenda: 10/26/2020 Final action: 11/4/2020
Title: Request to approve Change Order No 1 for contract 36-20 for 2019 AWWTP Electrical Distribution Upgrades Phase 2 project for refeeding and removal of the E-Building's transformers and motor control centers in the amount of $95,800 resulting in a decrease of the contingency from $230,590 to $134,790. No change to the overall contract amount
Attachments: 1. 2020 AWWTP Electrical Distribution Upgrades Phase 2 Change Order #1.pdf

Title

Request to approve Change Order No 1 for contract 36-20 for 2019 AWWTP Electrical Distribution Upgrades Phase 2 project for refeeding and removal of the E-Building's transformers and motor control centers in the amount of $95,800 resulting in a decrease of the contingency from $230,590 to $134,790.  No change to the overall contract amount