Title: Contract 43-20 was awarded to Bodart Electrical Service for the 2020 Pierce Park Lighting Upgrades Project-Phase One in the amount of $156,564 with a contingency of 10%. One deduction change order was issued in the amount of $4,091 because actual conduit and wire quantities were less than required in the bid documents. Payments to date total $144,849.54. Request to issue the final contract payment of $7,623.66

Title

Contract 43-20 was awarded to Bodart Electrical Service for the 2020 Pierce Park Lighting Upgrades Project-Phase One in the amount of $156,564 with a contingency of 10%. One deduction change order was issued in the amount of $4,091 because actual conduit and wire quantities were less than required in the bid documents. Payments to date total $144,849.54. Request to issue the final contract payment of $7,623.66