File #: 20-1238    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 9/17/2020 In control: Finance Committee
On agenda: 9/21/2020 Final action: 9/21/2020
Title: Change Order No. 1 to contract 96-19, Unit Z-19 Sewer & Water - Spartan, Sommers, & Haymeadow, for adjustments based on final measured quantities, added sewer outfall cleaning and additional grading work in the amount of $22,115. This change order reduces contingency from $45,000 to $22,885. Overall contract amount remains unchanged
Attachments: 1. Unit Z-19 Change Order No. 1.pdf

Title

Change Order No. 1 to contract 96-19, Unit Z-19 Sewer & Water - Spartan, Sommers, & Haymeadow, for adjustments based on final measured quantities, added sewer outfall cleaning and additional grading work in the amount of $22,115. This change order reduces contingency from $45,000 to $22,885. Overall contract amount remains unchanged