File #: 20-1237    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 9/17/2020 In control: Finance Committee
On agenda: 9/21/2020 Final action: 9/21/2020
Title: Change Order No. 1 to contract 17-20, Unit U-19 North Edgewood Sanitary Lift Station, for a transformer upgrade, relocation of VFD to Generator room and additional stone backfill for sanitary trenching in the amount of $12,500. This change order reduces contingency from $40,000 to $27,500. Overall contract amount remains unchanged
Attachments: 1. Unit U-19 Change Order No. 1.pdf

Title

Change Order No. 1 to contract 17-20, Unit U-19 North Edgewood Sanitary Lift Station, for a transformer upgrade, relocation of VFD to Generator room and additional stone backfill for sanitary trenching in the amount of $12,500. This change order reduces contingency from $40,000 to $27,500. Overall contract amount remains unchanged