Title: Contract 23-20 was awarded to Blue Sky Contractors for the 2020 Facilities and Grounds Operations Center Modification project in the amount of $200,529 with a contingency of $20,000. One change order was issued in the amount of $17,541. Request to issue the final contract payment of $29,752.23

Title

Contract 23-20 was awarded to Blue Sky Contractors for the 2020 Facilities and Grounds Operations Center Modification project in the amount of $200,529 with a contingency of $20,000.  One change order was issued in the amount of $17,541. Request to issue the final contract payment of $29,752.23