On agenda: 6/22/2020 Final action: 7/1/2020
Title: Request to approve Contract Amendment/Change Order No. 1 to Contract No. 24-20, Unit W-20 Sewer & Water Reconstruction No. 1 for additional time and materials required to remove an existing concrete encased sanitary sewer main in Glendale Avenue in the amount of $53,200 resulting in a decrease to contingency from $71,180 to $34,498. Overall contract increases from $3,630,180 to $3,646,698
Attachments: 1. Unit W-20 Change Order No. 1.pdf

Title

Request to approve Contract Amendment/Change Order No. 1 to Contract No. 24-20, Unit W-20 Sewer & Water Reconstruction No. 1 for additional time and materials required to remove an existing concrete encased sanitary sewer main in Glendale Avenue in the amount of $53,200 resulting in a decrease to contingency from $71,180 to $34,498.  Overall contract increases from $3,630,180 to $3,646,698