Title:
|
Change Order No. 1 to contract 85-19, Unit BB-19 Edgewood Drive Sanitary Sewer for additional quantity of steel casing pipe due to existing stone embankments in the amount of $5,000 resulting in a decrease to contingency from $47,900 to $42,900. No change to overall contract amount
|