File #: 20-0207    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 2/13/2020 In control: Finance Committee
On agenda: 2/19/2020 Final action: 2/19/2020
Title: Change Order No. 1 to contract 110-19 for Unit AA-19 Bear Creek Culvert and Spartan/Sommers Retaining Wall to reallocate funds to 2019J Brown & Caldwell contract to redesign wall due to construction error. This change order reduces contingency by $10,548. from $58,116 to $47,568. Overall contract amount is reduced from $639,279 to $628,731.
Attachments: 1. Unit AA-19 Change Order No. 1.pdf

Title

Change Order No. 1 to contract 110-19 for Unit AA-19 Bear Creek Culvert and Spartan/Sommers Retaining Wall to reallocate funds to 2019J Brown & Caldwell contract to redesign wall due to construction error.  This change order reduces contingency by $10,548. from $58,116 to $47,568. Overall contract amount is reduced from $639,279 to $628,731.