Title: Contract 121-19 was awarded to Highway Landscapers, Inc for the 2019 Vulcan Heritage Phase 2 Hardscapes Renovation project in the amount of $57,000 with a contingency of $5,000. No change orders were issued. Payments to date total $54,150. Request to issue the final contract payment of $2,850

Title

Contract 121-19 was awarded to Highway Landscapers, Inc for the 2019 Vulcan Heritage Phase 2 Hardscapes Renovation project in the amount of $57,000 with a contingency of $5,000.  No change orders were issued.  Payments to date total $54,150. Request to issue the final contract payment of $2,850