Title:
|
Request to approve contract amendment and Change Order No. 1 to contract 36-19 for Unit Y-19 Sewer and Water Reconstruction No. 3 for additional measured sanitary sewer and storm sewer construction quantities in the amount of $30,000.00 resulting in a reduction in contingency from $79,088.65 to $51,901.28. Overall contract increases from $1,660,861.65 to $1,663,674.28.
|