Title:
|
Contract 31-19 was awarded to Sommers Construction Co, Inc for the AWWTP Entrance Road and Gate Upgrades project in the amount of $326,917 with a contingency of 12%. One change order was issued in the amount of $16,160. Payments to date total $209,085.33. Request to issue the final contract payment of $133,991.94
|