Title:
|
Change Order #1 to August Winter and Sons in the amount of $23,835 for the Chemical Systems Upgrade Project resulting in the construction contract being increased to $722,335 and a decrease in contingency from $104,775 to $80,940.
Increase project final completion date from May 14, 2019 to August 31, 2019
|