Title: Request to approve contract amendment/Change Order No. 1 to Contract 77-19 for Kernan Avenue/East South River Street Storm Sewer Construction for additional funding to complete permanent concrete surface restoration in lieu of temporary asphalt in the amount of $121,841 with an increase in contingency from $50,000 to $70,000. Overall contract increases from $904,655 to $1,046,496
Attachments: 1. Unit T-19 Change Order No.1.pdf

Title

Request to approve contract amendment/Change Order No. 1 to Contract 77-19 for Kernan Avenue/East South River Street Storm Sewer Construction for additional funding to complete permanent concrete surface restoration in lieu of temporary asphalt in the amount of $121,841 with an increase in contingency from $50,000 to $70,000.  Overall contract increases from $904,655 to $1,046,496