File #: 19-0724    Version: 1 Name:
Type: Presentation Status: Filed
File created: 5/15/2019 In control: Finance Committee
On agenda: 5/20/2019 Final action: 6/5/2019
Title: Approve Change Order No. 1 to contract 29-19 for Unit X-19 Prospect Avenue Sewer & Water Reconstruction No. 2 for additional material costs due to contaminated soils encountered during construction in the amount of $15,935 resulting in a decrease to contingency from $72,057 to $56,122. No change to overall contract amount
Attachments: 1. Unit X-19 Change Order No.1.pdf

Title

Approve Change Order No. 1 to contract 29-19 for Unit X-19 Prospect Avenue Sewer & Water Reconstruction No. 2 for additional material costs due to contaminated soils encountered during construction in the amount of $15,935 resulting in a decrease to contingency from $72,057 to $56,122.  No change to overall contract amount