Title:
|
Approve Change Order No. 1 to contract 29-19 for Unit X-19 Prospect Avenue Sewer & Water Reconstruction No. 2 for additional material costs due to contaminated soils encountered during construction in the amount of $15,935 resulting in a decrease to contingency from $72,057 to $56,122. No change to overall contract amount
|