Contract 39-18 was awarded to Miron Construction Co. Inc for the 2018 MSB Locker Room Remodeling project in the amount of $314,713 with a contingency of $12,702. Two change orders were issued in the amount of $6,668.24. Payments to date total $313,346.71. Request to issue the final contract payment of $8,034.53
|