Title:
|
Contract 1-18 was awarded to Kruczek Construction, Inc for $1,477,778 with a contingency of $73,889 for Telulah Avenue Sewer/Water Construction project. Change orders were approved totaling $19,500. Final contract amount is $1,497,278 with a contingency of $54,389. Payments issued to date total $1,436,892.39. Request final payment of $39,817.94
|