Title: Contract 43-18 was awarded to Dorner, Inc for $880,170 with a contingency of $44,009 for Evergreen Drive Storm Sewer Construction project. Payments issued to date total $733,840.75. Request final payment of $19,747.10

Title

Contract 43-18 was awarded to Dorner, Inc for $880,170 with a contingency of $44,009 for Evergreen Drive Storm Sewer Construction project.  Payments issued to date total $733,840.75.  Request final payment of $19,747.10