File #: 19-0034    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 1/3/2019 In control: Finance Committee
On agenda: 1/7/2019 Final action: 1/7/2019
Title: Change Order #5 to August Winter and Sons in the amount of $729 for the Iron Salt Rehabilitation Project resulting in the construction contract being increased from $421,641 to $422,370 and the contingency being reduced from $36,720 to $35,991 and extend the Final Completion date from November 15, 2018 to November 30, 2018
Attachments: 1. Iron Salt Room Rehab Improvements Change Order 5.pdf

Title

Change Order #5 to August Winter and Sons in the amount of $729 for the Iron Salt Rehabilitation Project resulting in the construction contract being increased from $421,641 to $422,370 and the contingency being reduced from $36,720 to $35,991 and extend the Final Completion date from November 15, 2018 to November 30, 2018