Title: Change order No. 3 to contract 03-17 for Unit H-17 Northland Pond Construction for additional French drains in unstable slopes and additional excavation and disposal of contaminated soils in the amount of $39,916 resulting in a decrease to contingency from $97,381 to $57,434. No change to overall contract amount.
Attachments: 1. H-17 Contract Change Order Form 3_11-19-2018.pdf

Title

Change order No. 3 to contract 03-17 for Unit H-17 Northland Pond Construction for additional French drains in unstable slopes and additional excavation and disposal of contaminated soils in the amount of $39,916 resulting in a decrease to contingency from $97,381 to $57,434.  No change to overall contract amount.