File #: 18-1530    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 10/17/2018 In control: Finance Committee
On agenda: 10/22/2018 Final action: 11/7/2018
Title: Request to award 2017 B-Building Boiler Replacement project contract to Great Lakes Mechanical, Inc in the amount of $790,587 with a contingency of 9% for a project total not to exceed $860,000 and approve the following 2018 budget adjustment: WWTP Improvement Project - $110,000 WWTP Hardscapes Project - $250,000 WWTP Electrical Distribution Project - $150,000 B-Building Boiler Replacement Project +$510,000 to reflect transfer of positive balances from WWTP projects to the B-Building Boiler Replacement project
Attachments: 1. 2018 WWTP Bio-Gas Boiler Project.pdf

Title

Request to award 2017 B-Building Boiler Replacement project contract to Great Lakes Mechanical, Inc in the amount of $790,587 with a contingency of 9% for a project total not to exceed $860,000 and approve the following 2018 budget adjustment:

 

WWTP Improvement Project                                                                                                                                                   - $110,000

WWTP Hardscapes Project                                                                                                                                                   - $250,000

WWTP Electrical Distribution Project                                                                                    - $150,000

B-Building Boiler Replacement Project                                                                                    +$510,000

 

to reflect transfer of positive balances from WWTP projects to the B-Building Boiler Replacement project