Title: Warner Street, from College Avenue to Henry Street, be reconstructed with asphalt pavement and concrete curb & gutter to a width of 33’ from back of curb to back of curb, which is the same width as the existing street. Existing parking provisions within the project limits will remain unchanged. New concrete sidewalk would be constructed along the west side of Warner Street within the project limits.

Title

Warner Street, from College Avenue to Henry Street, be reconstructed with asphalt pavement and concrete curb & gutter to a width of 33’ from back of curb to back of curb, which is the same width as the existing street.  Existing parking provisions within the project limits will remain unchanged.  New concrete sidewalk would be constructed along the west side of Warner Street within the project limits.