Title:
|
Request for approval of Bid Packages and project related expenses into the Guaranteed Maximum Price Amendment to Miron Construction for the Jones Park Project for a contract not to exceed $3,753,690 plus a contingency of 5% for a contract not to exceed $3,937,861 and approval of the following 2018 Budget adjustment:
Public Works Capital Project Fund
Debt Proceeds - $887,558
Mobility Study Implementation Project - $887,558
Facilities Management Capital Projects Fund
Jones Park Project +$887,558
Debt Proceeds +$887,558
transfer funds from the Mobility Study Implementation Project to the Jones Park Project
|