Title:
|
Contract 73-16 was awarded to August Winter & Sons, Inc for $213,775 with a contingency of $21,378 for Arbutus Park Stormwater Lift Station Reconstruction. Change orders were approved totaling $45,925. Final contract amount is $259,700 with a contingency of $25,878. Payments issued to date total $246,715. Request final payment of $12,985.
|