Title: Contract 55-17 was awarded to VOE Power and Systems, LLC for the 2017 MSB Fire Alarm project in the amount of $68,177 with a contingency of $10,000. One change order was issued in the amount of $773. Payments issued to date totaled $65,502. Request to issue the final contract payment of $3,447.48