File #: 17-1774    Version: 1 Name:
Type: Presentation Status: Filed
File created: 11/2/2017 In control: Finance Committee
On agenda: 11/6/2017 Final action: 11/6/2017
Title: Change Order No. 2 to contract 43-17 for Unit AA-17/X-17 Cotter Street Stormwater improvements/Sewer and Water Reconstruction No. 2 for an additional storm sewer main and manhole quantities in the amount of $5,695 resulting in a decrease to contingency from $69,078 to $63,383. No change to overall contract amount
Attachments: 1. Unit AA-17 ~ X-17 Change Order No.2.pdf

Title

Change Order No. 2 to contract 43-17 for Unit AA-17/X-17 Cotter Street Stormwater improvements/Sewer and Water Reconstruction No. 2 for an additional storm sewer main and manhole quantities in the amount of $5,695 resulting in a decrease to contingency from $69,078 to $63,383.  No change to overall contract amount